DRDGOLD [logo]

Blyvoor

Blyvoor is situated on the north-western edge of the Witwatersrand Basin, to the south of the town of Carletonville and 70km south-west of Johannesburg, in North West Province. The mine has underground and surface operations and a gold plant. The first ore was raised in 1942.

Blyvoor has two main gold-bearing horizons: the Carbon Leader Reef (CLR), which is one of the principal orebodies of the Carletonville goldfield; and the Main Reef, which is some 75m above the CLR horizon. The reef formations have a thickness of between 5cm and 20cm. Recently there has been a shift in focus to mining the Main Reef.

Underground ore is mined by traditional drill, blast and scape narrow-reef mining methods. The operation is a combination of the workings of Blyvoor and Doornfontein mines and this allows several means of access, with four surface shafts still available and open.

Apart from the underground operations, production comes from waste rock stockpiles and the retreatment of surface tailings with the latter accounting for approximately 30% of current gold production.

Blyvoor’s carbon-in-leach (CIL) plant has a plant capacity of around 400 000 tonnes a month.

Life of mine is projected until 2030, but the resource at Blyvoor is so widespread that production could extend for many years beyond that, depending on the prevailing gold price and exchange rate.

In 2009 total gold production decreased by 8% to 129 473 ounces (2008:141 172 ounces) reflecting an 8% drop in throughput to 4 036 000 tonnes (2008:4 406 000 tonnes). Overall yield, however, held steady at 1.0 grams per tonne (g/t). Operating profit was 17% higher at R176.2 million (2008: R150.9 million) and capital expenditure increased by 30% to R97.5 million (2008: R74.8 million).

Growth projects

Mining from the Way Ahead Project (formerly known as Phase 2 of the No 2 Sub-shaft Project) – to access the orebody between 27 and 35 levels from No 5 Shaft – began the first week of October 2008. Production build-up continued according to plan during 2009 with the goal of 1 200m2 for the end of the financial year being exceeded.

The purpose of No 6 shaft's 15/29 Incline Project is to open up the Main Reef and CLR reserves of some 540 000m2. Supplier delays have had a negative impact on this project. The upper portion is in production but overall build-up has been slower than anticipated. Deeping of the incline to facilitate smoother loading of reef is in progress.

Blyvoor underground plan

Blyvoor: Underground plan

Key statistics
   12 months to
30 Jun 2009
12 months to
30 Jun 2008
Ore milled   
  Undergroundt’000 603 687
  Surfacet’000 3 433 3 719
  Totalt’000 4 036 4 406
Yield   
  Undergroundg/t 4.59 4.70
  Surfaceg/t 0.37 0.31
  Totalg/t 1.00 1.00
Gold produced   
  Undergroundoz 88 898103 813
 kg2 765 3 229
  Surfaceoz 40 575 37 359
 kg1 262 1 162
  Totaloz 129 473141 172
 kg4 0274 391
Cash operating costs   
  UndergroundUS$ per oz 878 772
 ZAR per kg 255 517 181 518
 ZAR per tonne 1 172 853
  SurfaceUS$ per oz 337 387
 ZAR per kg 98 124 90 971
 ZAR per tonne 3628
  TotalUS$ per oz 709670
 ZAR per kg 206 191168 034
 ZAR per tonne 206157
Gold and silver revenue(US$ million) 112.6n/a
 (ZAR million) 1 018.5n/a
Cash operating profitUS$ million 20.821.4
 ZAR million 188.2156.4
Capital expenditure (net)US$ million 10.710.2
 ZAR million 97.274.8
© 2010 DRDGOLD Limited